Skip to main content

What is the slab minimum grade concrete to de-shuttering in 14 days?

Minimum Concrete Grade for Slab De-shuttering in 14 Days — Practical Guide

Minimum Concrete Grade for Slab De-shuttering in 14 Days — Practical, Copyright-Free Guide

Short answer: there is no single universal “minimum grade” that guarantees safe de-shuttering in 14 days — but for typical reinforced floor slabs cast with ordinary Portland cement concretes, using a minimum grade of M20 (20 MPa characteristic compressive strength) combined with good curing often achieves the necessary 14-day strength to remove formwork safely, provided in-situ or companion specimen tests confirm required strength (commonly around 65–75% of design strength at 14 days). This article explains the reasoning, gives worked examples, describes testing and curing procedures, and outlines safe de-shuttering practices.

Why the question matters

Formwork removal (de-shuttering) is one of the most critical stages in concrete construction. Remove props too early and the slab may sag, crack, or fail; wait too long and the schedule suffers and costs rise. Contractors, site engineers, and clients want practical guidance: what concrete grade will be safe to remove formwork at 14 days? The correct answer depends on design strength, expected early strength gain, curing, loading conditions, and the acceptable safety margin.

Key concepts you should know

Characteristic compressive strength (fck)

Concrete mix grades are described by their characteristic compressive strength, e.g., M15, M20, M25, where the number indicates fck in MPa at 28 days (for standard mixes using OPC). A grade M20 has a characteristic strength of 20 megapascals measured at 28 days.

Early-age strength gain

Concrete gains strength with time. Typical OPC concretes will achieve a portion of their 28-day strength at earlier ages. The fraction at 7 or 14 days depends on mix design, cement type, curing temperature and humidity, and admixtures. Common practice and many codes use a strength ratio — the percentage of 28-day strength achieved at a given age — to judge safety for formwork removal.

Required strength before de-shuttering

Engineers usually require the concrete to reach a specified fraction of fck or an absolute compressive strength before removing formwork. A frequently used practical rule is that slabs may be de-shuttered when the concrete attains approximately 65–75% of the 28-day design strength, depending on the design and loading. Another approach is to specify a minimum absolute strength in megapascals measured on companion cubes/cylinders tested at the strip time.

Typical practical targets at 14 days

Below are typical expected strength ranges after 14 days for ordinary mixes cured properly at normal temperatures (20–27 °C). Keep in mind these are approximate and vary by many factors.

  • M20 (20 MPa) — expected 14-day strength around 55–75% of 28-day strength → roughly 11–15 MPa
  • M25 (25 MPa) — expected 14-day strength roughly 14–18 MPa
  • M30 (30 MPa) — expected 14-day strength roughly 17–22 MPa

Note: these are general ranges. Modern mixes with higher cement content, Type II/III cements or positive admixtures (accelerators) can reach higher 14-day strengths; cold weather or poor curing reduces them.

Translating percentage to safety: a simple rule of thumb

Designers often specify that formwork supporting a member may be removed when the concrete attains a specified percentage (call it α) of fck. Common values for α range from 0.5 (50%) for non-load-bearing, lightly reinforced forms, up to 0.7–0.75 (70–75%) when early strength matters or when safety margins are tight. For slabs, many practitioners use α ≈ 0.7 as a conservative and practical target at 14 days.

So, if fck = 20 MPa (M20), 70% of that is 14.0 MPa. If companion cubes show ≥14 MPa at 14 days (with proper sampling), de-shuttering for typical slab formwork may be considered safe — again, depending on loads and construction sequence.

Worked examples

Example 1 — Residential slab, limited live load

Design: reinforced concrete slab for low-rise residential building. Grade chosen: M20 (fck=20 MPa). Engineer requires 70% of fck at formwork removal.

Calculation: 0.70 × 20 MPa = 14 MPa. If laboratory or site companion specimen tests show at least 14 MPa at 14 days and curing has been adequate, de-shuttering the slab is generally acceptable. Always ensure supports beneath the slab are not immediately removed if they carry additional structural parts.

Example 2 — Heavier use slab (commercial), prefer faster strength

Design: slab that will later support heavy finishes or early hoistings. Engineer selects M25 for extra margin. Target α = 0.75.

Calculation: 0.75 × 25 MPa = 18.75 MPa. Confirm companion samples reach ≈19 MPa at 14 days before removing formwork.

Minimum grade recommendation

Based on practical experience and typical early-age strength behaviour, a conservative recommendation for aiming to de-shutter slabs at 14 days without special accelerators or high-early strength cement is to use M20 or higher. M15 mixes may not reliably develop enough strength in 14 days under standard curing, especially in cooler climates.

Practical takeaway: if your schedule requires reliable 14-day stripping, design for at least M20 (preferably M25 if loads are higher or if you want more margin) and confirm with testing.

How to confirm strength on site

  1. Companion specimens (cubes or cylinders): Cast standard cubes/cylinders from the same batch, cure them under controlled conditions, and test at 14 days. Use the measured compressive strength as the basis for stripping decisions.
  2. Non-destructive testing (NDT): Tools like rebound hammers or ultrasonic pulse velocity can provide quick indications of relative strength in the field. NDT should be calibrated with lab tests; do not rely solely on NDT for a go/no-go decision.
  3. Manufacturer / supplier certificates: If you are using ready-mix supplied with traceable records and strength forecasts, include those in the decision but back up with on-site sampling where possible.

Important variables that affect early strength

  • Cement type and fineness: Rapid-hardening Portland cements or cements with higher early strength gain will reach the desired 14-day strengths faster than ordinary slow cements.
  • Water–cement ratio: Lower w/c yields higher early strength (if workability is maintained by admixtures).
  • Use of admixtures: Accelerators and high-range water reducers can speed early strength gain and improve workability.
  • Temperature: Concrete cured at higher temperatures gains strength faster; cold weather slows gain (use heaters or thermal blankets if needed).
  • Curing quality: Proper moist curing greatly improves early strength. Poor curing can reduce early strength dramatically.

Safe de-shuttering procedure (step-by-step)

  1. Check test results: Verify 14-day companion specimen strength meets the specified fraction or absolute value required by the engineer.
  2. Inspect slab surface and supports: Ensure the concrete surface appears sound, without excessive shrinkage cracking or localized distress.
  3. Plan sequence: Remove facing formwork first (edges and soffits) while keeping main props if required. For large spans, remove formwork in short stretches, not all at once.
  4. Retain props where needed: Even after shutter removal, keep temporary props under the slab until the structure reaches a self-supporting capacity per the construction sequence. Shoring removal is often staged over weeks.
  5. Monitor deflection: After removal, check for unexpected deflection or cracking; if observed, re-prop and investigate.

Cautions and common pitfalls

1. Rely on tests, not dates: The calendar age (14 days) is only meaningful if companion specimens confirm the required strength. 14 days does not universally equal safety.

2. Design loading matters: If the slab will immediately carry heavy loads (e.g., construction equipment), do not remove shoring just because the slab is 14 days old.

3. Weather effects: Rain, cold, or rapid drying reduce early strength. Protect and cure the slab properly.

4. Different parts of the structure behave differently: Beams and columns may require longer support than flat slabs even though their formwork might appear similar.

Recordkeeping and verification

Keep a clear record of batch numbers, mix proportions, curing schedule, companion specimen test reports, and onsite NDT readings. Good documentation helps the engineer justify a safe stripping decision and is essential if any later disputes arise.

Summary checklist before de-shuttering at 14 days

  • Companion cubes/cylinders show required strength (e.g., ≥70% fck).
  • Curing has been continuous and adequate for the first 7–14 days.
  • Site temperature and conditions were favourable or compensated for.
  • Loading after stripping will be controlled — no heavy loads immediately.
  • Engineer or qualified site staff have approved the stripping plan and sequence.

Conclusion

There is no one-size-fits-all numeric grade that guarantees safe de-shuttering at 14 days without considering mix design, curing, temperature, and evidence (tests). For ordinary reinforced slabs under standard conditions, pilots and experienced practitioners commonly use M20 as the minimum practical grade to aim for safe de-shuttering at 14 days — preferably combined with companion specimen confirmation that the concrete has reached roughly 70% of its 28-day strength. If you need faster stripping, use higher grade mixes, specialty cements, or approved accelerating admixtures and always verify with tests.

Comments

Popular posts from this blog

What are the typical reinforcement details of a cantilever slab?

  Cantilever slabs are a type of concrete slab that projects beyond the supporting beam. They are typically used in balconies, overhangs, and other structures where a cantilevered beam is required. The reinforcement for a cantilever slab is designed to resist the tensile forces that are generated when the slab is loaded. The main reinforcement is provided on the top of the slab, along the span direction. It is typically made of mild steel bars with a diameter of 12mm or 16mm. The main reinforcement is bent back at the support end to form a hairpin shape. This helps to anchor the reinforcement and prevent it from pulling out of the concrete. Distribution reinforcement is also provided on both the top and bottom of the slab. It is typically made of mild steel bars with a diameter of 8mm or 10mm. The distribution reinforcement helps to distribute the load evenly across the slab and prevent cracking. Stirrups are also provided at regular intervals along the length of the slab. They hel...

What is the plaster compressive strength of a mix 1:4 ratio?

 The compressive strength of a plaster mix with a 1:4 ratio is typically in the range of 3,000 to 3,500 psi (pounds per square inch). This means that a 1-inch cube of plaster made with this mix would be able to withstand a compressive force of up to 3,000 to 3,500 pounds before it would break. The actual compressive strength of a 1:4 plaster mix will vary depending on the type of cement used, the quality of the sand, the water-cement ratio, and the curing conditions. However, in general, a 1:4 plaster mix will have a compressive strength that is sufficient for most interior applications. Here is a table of the compressive strength of a 1:4 plaster mix after different curing periods: Curing Period Compressive Strength (psi) 7 days 2,500 14 days 3,000 28 days 3,500 As you can see, the compressive strength of the plaster increases with the curing period. This is because the cement in the plaster continues to harden over time. So, if you want the strongest possible plaster, you shoul...

What is the definition of shear strength (σ) in Mohr's Circle?

  In Mohr's Circle, shear strength (σ) is defined as the maximum shear stress acting on a plane in the overall 2-D stressed body. It is equal to one half the difference of the major and minor principal stresses, and is represented by the radius of Mohr's Circle. The equation for shear strength in Mohr's Circle is:σ = (σ1 - σ2) / 2 where:     σ1 is the major principal stress     σ2 is the minor principal stress The shear strength is important in engineering because it is a measure of the ability of a material to resist shear forces. Materials with high shear strength are more resistant to failure in shear. In Mohr's Circle, shear strength is plotted as the ordinate (y-coordinate) of a point on the circle. The abscissa (x-coordinate) of the point represents the normal stress on the plane. The center of the circle represents the average of the major and minor principal stresses. Mohr's Circle is a useful tool for visualizing the state of stress at a point in a mate...